Team CHHRI believes in taking a professional approach and chose the difficult route of forming a section 42 company rather than a trust. Subsequently, our dedicated team of individuals had a detailed discussion and hired a local company that represents Ernst & Young.
The following is a summary of the total proposed cost of the project:
Details | PKR | USD | % |
Land | 80,000,000 | 792,079 | 7.28 |
Building & Civil Work | 337,300,000 | 3,339,604 | 30.68 |
Medical & Support Equipment | 617,800,000 | 6,116,832 | 56.20 |
Furniture & Fixture | 6,300,000 | 62,376 | 0.57 |
Information System | 10,900,000 | 107,921 | 0.99 |
Vehicles | 9,900,000 | 98,020 | 0.90 |
Working Capital | 16,200,000 | 160,396 | 1.47 |
Pre-Operating Cost | 20,900,000 | 206,931 | 1.90 |
1,099,300,000 | 10,884,158 | 100 |